Ahead of the upcoming weather, we have 89 of 93 major drainage pumps and 51.5MW of 25Hz power available. Turbine 4 is currently out of service due to a mechanical issue. See updates and more information on our Pumping and Power Dashboard. 📷swbno.org/Projects/Pumpi…

Ahead of the upcoming weather, we have 89 of 93 major drainage pumps and 51.5MW of 25Hz power available.

Turbine 4 is currently out of service due to a mechanical issue.

See updates and more information on our Pumping and Power Dashboard.
📷swbno.org/Projects/Pumpi…
SWB New Orleans (@swbneworleans) 's Twitter Profile Photo

Five minutes now will help your future self save time.🕜 Grab your latest water bill & use the info there to sign up for our new online Customer Portal. With an account, you can easily pay your bill, view previous bills, link multiple accounts & more. youtube.com/watch?v=8LL29A…

SWB New Orleans (@swbneworleans) 's Twitter Profile Photo

Ahead of the upcoming weather, we have 88 of 93 major drainage pumps and 51.5MW of 25Hz power available. Turbine 4 is currently out of service due to a mechanical issue. See updates and more information on our Pumping and Power Dashboard. swbno.org/Projects/Pumpi…

Ahead of the upcoming weather, we have 88 of 93 major drainage pumps and 51.5MW of 25Hz power available.

Turbine 4 is currently out of service due to a mechanical issue.

See updates and more information on our Pumping and Power Dashboard.

swbno.org/Projects/Pumpi…
SWB New Orleans (@swbneworleans) 's Twitter Profile Photo

We have 88 of 93 major drainage pumps and 67.5MW of 25 Hz power available. For peak demand, our system requires 44MW of 25 Hz power. See updates and more information on our Pumping and Power Dashboard. 🔗swbno.org/Projects/Pumpi…

We have 88 of 93 major drainage pumps and 67.5MW of 25 Hz power available. For peak demand, our system requires 44MW of 25 Hz power.

See updates and more information on our Pumping and Power Dashboard. 🔗swbno.org/Projects/Pumpi…